Construction Progress
Artemis, taking shape.
Follow the construction of Artemis as the development takes shape on the waterfront in Artemida.
Current Construction Focus
Interior partitions
In progress
Building services
In progress
Hydraulic works
First phase nearing completion
Latest update
First-floor interiors taking shape
First-floor interiors continue to take shape as plasterboard partitions advance alongside the installation of water, sewage, cooling and heating pipework, while the first phase of hydraulic works moves toward completion.
Site notes · 14–20 SEPT
- Partition walls
- First-floor plasterboard partitions progressing
- Building services
- Water and sewage pipework installation; first-phase hydraulic works nearing completion
- Climate systems
- Cooling and heating pipework installation
Construction journal
Interior works continue
Interior works continue across the residences, with first-floor partition walls taking shape alongside the installation of water, sewage, cooling and heating pipework.
Site notes · 09–16 SEPT
- Partition walls
- First-floor internal layouts progressing
- Building services
- Water and sewage pipework installation
- Climate systems
- Cooling and heating pipework progressing
Interior works progressing
Interior partitioning, building services and ceiling works are progressing across the residences as the internal layouts continue to take shape.